Hi,

We are starting a survey and currently doing pilot survey. So, after every pilot survey there is some changes in the questionnaire. The data collect during pilot survey has finalized and sent. Can we import in the data collected in new update questionnaire to edit.

Thanks

In my experience, we had done the same action in survey activity. At this time, we have happened previous data did not send to server from tablet. So we were uploaded old question to the server and then resend data from the tablet. If you want to change the new question, the first step you will send collected previous data from the tablet and then you can upload to the server for a new question and download new question for data collection.

So, there will be two set of data for new and old questionnaire.

If you have done collected old data, you can add a new question to the old question but you will need to download for the new question from tablets.